Northeast Health Wangaratta (NHW) has reached a significant milestone in its Key Worker accommodation development, with the project successfully achieving Lock-Up Completion ahead of the originally anticipated February 2026 timeframe.
This milestone follows the completion of framing works announced in October 2025 and reflects the strong performance of our contractors and effective project coordination to date.
Northeast Health Wangaratta Executive Director People and Corporate Operations Kim Bennetts said reaching lock-up ahead of schedule is an important achievement for the project.
“Achieving lock-up earlier than anticipated is a great result and reflects the strong collaboration between our project team and our contractors,” Ms Bennetts said. “This development is a key part of how we support our workforce by improving access to quality housing, which in turn helps us attract and retain skilled healthcare professionals in our region.”
With lock-up now complete, the project will progress into the fixing phase, which includes installation of internal joinery, fittings and fixtures, along with completion of remaining internal works. This phase will prepare the building for final inspections and commissioning activities.
Subject to continued progress and no unforeseen issues, the project remains on track to achieve Practical Completion and handover prior to 30 June 2026, in line with the approved program and funding timelines.
The staff housing development forms part of NHW’s broader commitment to supporting staff and strengthening workforce sustainability, helping ensure the ongoing delivery of exceptional healthcare for the North East community.
NHW thanks the project team, contractors and partners for their continued efforts and acknowledges the community for their patience and support as construction progresses.